Time critical delivery

Our client had the unenviable task of delivering a major construction project within an uninterruptible operational environment. They knew that a lack of integration and poor co-ordination had left the project 8 weeks behind schedule and the overall programme 3 months behind its delivery schedule.

We coached the project teams in our improvement methodologies and worked together to make a number of key operational changes:

  • Production targets were set for all of the critical path packages
  • A real-time delay data recording system was introduced, creating a culture of instant feedback and remedy and helping to actively reduce production delays
  • New shift planning processes were introduced
Together, these changes helped to realign the critical path and streamline the resourcing process. As a result, we entirely recovered the 3 month slippage and the programme was eventually handed over for testing 1 month early - a 4 month improvement within a 6 month period.